Before driving the ball mill shouldcheck the connection bolts are loose or not; if found to be loose, to bepromptly fastened.
1. Before driving the cement ball mill shouldcheck the connection bolts are loose or not; if found to be loose, to bepromptly fastened.
2. Check the lubrication point whether isreasonable, to ensure that the lubricant oil is suitable and clean. Inaddition, also check the transmission is normal and reliable, guards areintact.
3. Check whether there is any obstacle inthe rotating part or around the equipment and eliminate it.
4. Check the correct, press the startbutton to start the motor, pay attention to current changes. Continuous startof the ball mill shall not exceed two times, the first and second intervals of5 minutes or more. If the third start, must be with the electrician, fitterwith the inspection, before starting.
5. After the normal operation of the ballmill, water supply to the mine, the amount of steel balls according to theprovisions. Do not overload, idle time cannot exceed 15 minutes, so as not todamage the liner.
6. The operation should pay attention tocheck the cylinder leakage, carefully observe the current, voltage, feed, wateris normal.
7. Should check the motor and the spindleevery half hour, the spindle temperature cannot be greater than 60 °С, if foundthe problem should be promptly processed.
8. The ball mill stop should be stoppedbefore the mine, standby concentrate processing, and stop water. Wait untileverything is ready before shutting down.
9. After a period of operation, the cement mill ball should be selected for all, into the new ball, in order to ensure the ball milloperating efficiency.