I. Project overview:
Project address: Anyang, Henan, China
Product Name: Lump ore drying system
Production scale: annual output of 1 million tons of lump ore production line
Service scope: from the storage and transportation, drying and cooling of raw materials to the storage and transportation system of finished products, environmental dust collection system, tail gas dust removal, desulfurization and deodorization system, process design of electrical automation control system, plant planning, equipment supply, equipment installation and debugging, after-sales training and other one-stop technical services.
II. Project Description
"Anyang Iron and Steel" can produce steel products of more than 30 varieties, more than 2000 specifications and coking chemical products of medium and heavy plates, high-speed wires, medium and small profiles, etc. By the end of 2005, the total assets of the company were 11.736 billion yuan.
Adding lump ore evenly before cooling, drying moisture with waste heat, mixing lump ore and lump ore into the warehouse, completely solving a series of production problems such as feeding and screening caused by large moisture and powder of lump ore, and achieving good economic benefits.
The processing capacity of the first-phase lump ore drying system is 1 million tons per year. During the bidding, well-known suppliers in the industry are all scrambling to sign up, and 5 peers participate in the bidding. After three rounds of intense technical and commercial bid evaluation and negotiation for more than a month, Zheng mining machine finally won the bid in July.
III. Design principles
In the process of executing the contract, the seller shall fully communicate with the buyer, understand the working conditions, ensure that the process design conforms to the process plan jointly determined by the buyer and the seller, and ensure that the process design is reasonable, applicable, smooth and stable.
The seller shall comply with the current national mandatory standards and specifications in the process design. If there is any objection, the seller may be consulted and completed on time and on time according to the contract.
IV. Project implementation
After winning the bid, our engineering and technical personnel overcome a number of technical difficulties according to the technical requirements of the bidding documents, and carry out careful and meticulous engineering construction drawing design, which has been reviewed and approved at one time. In strict accordance with the requirements of the contract, the Project Department formulates rigorous implementation plans, equipment manufacturing, installation, shipping, debugging and other work. With the active cooperation and support of Party A's project department, the project department will finish the work on time and the debugging will be smooth.
In the trial production process, our after-sales service personnel have been resident on the site for more than 2 months, and have dealt with and eliminated on-site problems in a timely manner.
Positive working attitude, rigorous working style, excellent product quality and good after-sales service have won the recognition and praise from leaders and employees at all levels of Hanzhong zinc industry to Zheng mine.
Previous:Clay Disk Granulator