Small jaw crusher machine for stone crushing

In the process of installation and debugging,jaw crusher often causes unsafe hidden dangers in the subsequent production process due to operation mistakes or unqualified debugging. How to install and debug jaw crusher correctly?

Small jaw crusher machine for stone crushing

In the process of installation and debugging,jaw crusher often causes unsafe hidden dangers in the subsequent production process due to operation mistakes or unqualified debugging. How to install and debug jaw crusher correctly? Hope the following sharing by ZK CORP about theinstallation and debugging of the jaw crusher can help you.

First, jaw crusher empty test

1. The jaw crusher operates continuously for2 hours and the bearing temperature rise must not exceed 30°C.

2. Jaw crusher all fasteners should be solid,no loose phenomenon.

3. Flywheel, sheave running smoothly.

4. All the friction parts of the jaw crusherare free of scratches, chipping and grinding, and there are no abnormal sounds.

5. Jaw crusher discharge adjustment deviceshould be able to ensure that the discharge port adjustment range.

Second, jaw crusher loaded test

1. The crusher must not have periodic orsignificant impact or impact sounds.

2. Feeding particle size should meet thedesign requirements.

3. Continuous operation 8h, bearingtemperature rise shall not exceed 30 °C.

4. Crusher processing capacity and productsize should meet the design requirements.

5. There is no obvious movement between theadjustment seat and the rack ear seat.

Three, jaw crusher preparation before use

1. Check carefully whether there is enoughgrease in the connection of the thrust plate.

2. Carefully check that all fasteners aretight.

3. Carefully check the transmission belt isgood. If any unsafety is found, it should be replaced in time. When there isoil on the belt or pulley, apply a rag to clean the oil.

4. Check whether the protective device isgood. When insecurity is found, it should be promptly eliminated.

5. Check the crushing cavity for ore ordebris. If there is ore or debris, it must be cleaned to ensure that thecrusher cavity starts.

6. Check whether the lifting bolts arereturned, whether the gasket group is pressed tightly and whether the T boltsare tightened.

Fourth, jaw crusher pre-start inspectionmatters

1. After inspection, it is proved that allparts of the machine are in normal condition before starting.

2. Only allowed to start without load.

3. Before starting, must use bell or signalto warn in advance.

4. After starting, if any abnormality isfound, the operation should be stopped immediately. Do not restart the crusheruntil after the abnormalities have been identified and corrected.

Whatever the machine, it is not the amount ofwork, but the maintenance. Only when the equipment is properly maintained canhe exert his ideal working efficiency. Jaw crusher has relatively fewvulnerable parts. Pay attention to the crushing of materials to avoid majoraccidents during the operation of the machine.